Progress update of hive water project.

in HiveGhana3 months ago

photo_2024-06-21_23-38-26.jpg

I have some good news to share about the ongoing Hive borehole project from Nantong Kpawumo in Tamale, northern Ghana, in today's post.

I'm excited to showcase the amazing progress we've accomplished so far. The first phase of construction ended at the drilling stage. Phase two has seen the construction of a powerful concrete tower to house the poly tanks. After the tank seat is built, the wooden framework will be removed to expose a clean, finished structure. It will then be allowed to dry for a few days.

To give the project a finished appearance, we will then install tiling and run all the required pipes through the walls. We intend to keep you informed as the project moves forward. We appreciate you remaining with us.

photo_2024-06-21_23-38-22.jpg

photo_2024-06-21_23-38-17.jpg

I would like to express my gratitude for the countless hours put in by those working on the ground to get us to this stage. We are happy to see excitement spreading over the faces of the locals now that the water is flowing. This is what really gets us excited.

The response from the community to this advancement has been very positive. The people who live in Nantong Kpawumo have shown their sincere appreciation and happiness, frequently who gather at the project site to see every stage of the development. Their smiles and presence demonstrate how much this advancement meant to them. Many people will find that having access to clean water can significantly improve their everyday life by overcoming many of the obstacles they have faced for years.

photo_2024-06-21_17-10-55.jpg

photo_2024-06-21_17-11-04.jpg

photo_2024-06-21_17-11-01.jpg

photo_2024-06-21_17-11-00.jpg

Elders and prominent members of the community have also expressed their sincere gratitude, highlighting the project's potential to completely change the town. They talk about how their children's quality of life will improve, their health will improve, and agriculture will flourish. The joy and optimism in the air serve as a reminder of the significance of our work and the enormous impact it has on people's lives.


Completed Hive Boreholes in Ghana
1st hive borehole, Fawoade, Ghana

2nd hive borehole, Agona Bedomase, Ghana

3rd hive borehole, Anwomaso, Ghana

4th hive borehole: Pentecost sch Bremang, Ghana

5th hive borehole, Jamasi Dawu

6th hive borehole, Asamang

7th hive borehole, Asamang

8th hive borehole: Chichibon

9th hive borehole, Chanshegu

10th hive borehole, Gbamyamli

11th hive borehole, Kanvili-kukuo

12th hive borehole, Asamankama A

13th hive borehole: Asamankama B

14th hive borehole: Wadie Adwumakase

23swbmjn63JdgoyTVMeypUtHbiAkjs3GAwHXs1wMEKoziKTFSXubj9P8oTR41uZuAPJL4.png


Project : Construction of borehole
Location : Nantong Kpawumo, Ghana, West Africa
Sponsor : @valueplan
Project manager : @mcsamm & @collinz

23tmevZWMhchtBsod1PgadF28K2RxdXYvW2zRtHJTvFV3yV2Ah6tXH8swfwcm54ue93QL.png

Changing lives with hive.

Sort:  

This is beautiful Indeed....
I can see the project is going well ❤️‍🩹

Thanks dear

Oh woah! This is amazing @mcsamm . Its lots of energy, encouragement and zeal to be moving with these projects. May the Lord continue to direct and provide resources for these projects .

Lots of Blessings 😇

We have made some good progress

Really a big progress Boss. May the Lord continue to strengthen you all.
Happy Sunday and bless new week 😇❤️